    Default Whats required for a 'Final Residential Inspection'

    Hi all

    I've almost reached the end of a relocated house project, and have the Final Residential Inspection left. As I've self managed this, I really don't know what I need to do to pass the final hurdle. All other inspection, like bracing, drainage etc has been approved.

    This is the description:

    To check that all construction associated with the building consent
    has been completed; this includes painting and decorating; floor
    coverings; fixtures; fittings; electrical work; heating appliances; etc

    My consent was not specific on the painting, floor coverings, heating etc. So my question is, to what standard does the internal and external house need to be in? Does it need to be fully repainted inside and out? Does a stove need to be installed and a heat source?

    Power is running and so is water, driveways and fencing complete.

    Just need some guidance as to what exactly is required.

    Thanks in advance.

  2. #2
    Join Date
    Mar 2013
    Location
    Auckland
    Posts
    1,583

    Default

    You don't actually need a building consent for a relocation. (However, you may need a resource consent.)
    The councils happily tell people that you do, but MBIE determinations have held that relocations are not "building work" as the house has already been built. You only need a building consent for any new "building work" associated with the relocation (like the foundations, sewers etc.) that would normally require a consent due to being restricted work.

    Thus, councils are over-stepping when they require any upgrading as you've detailed.
    My blog. From personal experience.
    http://statehousinginnz.wordpress.com/

  3. #3
    Join Date
    May 2013
    Posts
    184

    Default

    My experience was it all needs to be painted. The floors which were resanded needed a PS3 to confirm 3 coats of polyurethane had been done. Silicone was checked for in wet areas. I was asked to provide a product warranty on some roofing material. A few other things were noted but were not part of the consent and I had to write a letter to confirm no work was carried out on those areas.

  4. #4

    Default

    Quote Originally Posted by TheLibrary View Post
    My experience was it all needs to be painted. The floors which were resanded needed a PS3 to confirm 3 coats of polyurethane had been done. Silicone was checked for in wet areas. I was asked to provide a product warranty on some roofing material. A few other things were noted but were not part of the consent and I had to write a letter to confirm no work was carried out on those areas.
    Thanks guys. The houses were in pretty good condition when I got them.

    So a few cracks etc from the move which have been touched up and painted. Apart from that, we have not touched anything. From your comments , I will need to spend a little more time in the bathroom just retouching cracks and silicone.

    We had second hand building reports completed on the houses, and they also noted minimal work was required in that report.

    Did you recall if you needed to repaint the outside too? And whether there was a need for a heat source? Any other little fish hooks that you can recall would be good, as I just want to be covered.

  5. #5

    Default

    look at the building consent.
    that defines the building work which is what the council need to inspect. this includes foundation electrical work certificate and drainage



    you may also have had a resource consent which may have conditions on what happens to the houses.. colour insulation fencing etc

  6. #6

    Default

    Quote Originally Posted by John the builder View Post
    look at the building consent.
    that defines the building work which is what the council need to inspect. this includes foundation electrical work certificate and drainage



    you may also have had a resource consent which may have conditions on what happens to the houses.. colour insulation fencing etc
    We were able to negotiate our way out of a resource consent, as the overland flow path was minor. So no conditions there.

    My building consent didn't contain any requirements, apart from foundations, drainage and a 'final residential inspection.' The plans that were approved also had no specs or upgrades that were required.

    I've uploaded the schedule of inspections in case this helps. https://ibb.co/jzzxxK



  7. #7
    Join Date
    May 2013
    Posts
    184

    Default

    If you google final checklist and auckland council you should find something. It was a general overall inspection. I would get the statements from your tradesman or the builder may have them. Either way, if you dont pass, they leave you with a list of things to do. They add it to the bill, but it removes the stress if you are not familiar with the process.

  8. #8

    Default

    I agree with the lib
    while the final insp list discusses painting etc this is a general requirement that would relate to say a new house (painting strictly wet areas)


    I think you should call the inspection but keep the inspector focused on the consented work and maintain your position that internal works are not in the consent and under schedule 1 (exempt from requirement for consent)

  9. #9
    Join Date
    Mar 2013
    Location
    Auckland
    Posts
    1,583

    Default

    Quote Originally Posted by TheLibrary View Post
    The floors which were resanded needed a PS3 to confirm 3 coats of polyurethane had been done.
    What the hell? Floor treatments are not a restricted activity for which a consent is required. So how do they justify asking for a producer statement?
    I redid a whole bathroom, replacing all the sanitary fixtures and moving them around. No consent required. Therefore I certainly didn't inform the council that I was also sanding and polishing the floors (which I did myself). If this sort of info is not required for houses already in situ, how can it be required for houses being relocated?
    My blog. From personal experience.
    http://statehousinginnz.wordpress.com/

  10. #10
    Join Date
    Jan 2010
    Location
    Hibiscus Coast
    Posts
    1,714

    Default

    Not sure where you are but have you put cladding on the base to cover the piles? If so Akld Council expect either timber battens or fibrolite sheets to be painted. If using fibrolite must have vents at specified distances. Also they check for smoke alarms! Yes believe me they do!
    You should also have all your producer statements in the file, and LBP details need to be sighted.


 

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Similar Threads

  1. Replies: 13
    Last Post: 23-02-2018, 06:59 PM
  2. Replies: 11
    Last Post: 12-10-2015, 09:45 AM
  3. Newly built house - moving in after final inspection
    By sungsoonz in forum Property Investment (NZ)
    Replies: 33
    Last Post: 14-04-2014, 02:34 PM
  4. Final inspection went not as planned need advice!
    By jovanov in forum Tenant Stuff (NZ)
    Replies: 33
    Last Post: 23-10-2013, 11:37 AM
  5. Rude agent and final inspection
    By reina in forum Tenant Stuff (NZ)
    Replies: 4
    Last Post: 27-12-2010, 07:11 PM
  6. Advise please, landlord changes mind after final inspection!!
    By mnminthevilla in forum Tenant Stuff (NZ)
    Replies: 17
    Last Post: 12-07-2010, 11:57 AM
  7. Replies: 19
    Last Post: 13-05-2009, 10:02 PM
  8. Full inspection report required for insurance
    By fudosan in forum Property Investment (NZ)
    Replies: 4
    Last Post: 19-08-2005, 03:58 AM
  9. Apartment Inspection Required?
    By dino440 in forum Finance, legal and tax (NZ)
    Replies: 2
    Last Post: 24-02-2005, 09:05 AM
  10. Property Web Links
    By muppet in forum Property Investment (NZ)
    Replies: 1
    Last Post: 09-12-2003, 04:45 PM

Tags for this Thread

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •