Hi I have signed the conditional S and P Agreement; however the LIM has two statements which are confusing me
- Requisition: Spouting requires extending into rainheads Clips ALS downpipes: application status is Dormant
- Building Permit : Dwelling : Status Issued
Status notes:
Building permit Issued- Permit issued prior to Building Act 1991 taking effect. CCC were not required
Construction Review- Consent approved but a final code of compliance for this property has not been issued
how do I be sure that this does not bite me in future.
Also, neither the LIM nor title have the document that shows the original house design so not sure would that be an issue as the property has an ensuite and the vendor and agent says that it is legal.
Please advise ....
- Requisition: Spouting requires extending into rainheads Clips ALS downpipes: application status is Dormant
- Building Permit : Dwelling : Status Issued
Status notes:
Building permit Issued- Permit issued prior to Building Act 1991 taking effect. CCC were not required
Construction Review- Consent approved but a final code of compliance for this property has not been issued
how do I be sure that this does not bite me in future.
Also, neither the LIM nor title have the document that shows the original house design so not sure would that be an issue as the property has an ensuite and the vendor and agent says that it is legal.
Please advise ....
Comment