Hi,
I purchased a house & land package and it's about 1 month away to completion.
I hear some people move in even before CCC is issued as long as house passes final council inspection
as it takes at least 4 weeks to get CCC issued.
Is it 100% the case that the house will be issued with CCC if it passes the final inspection?
I obviously want to move in as early as possible but I do not want to take any risks at the same time.
Thanks in advance for sharing your thoughts.
I purchased a house & land package and it's about 1 month away to completion.
I hear some people move in even before CCC is issued as long as house passes final council inspection
as it takes at least 4 weeks to get CCC issued.
Is it 100% the case that the house will be issued with CCC if it passes the final inspection?
I obviously want to move in as early as possible but I do not want to take any risks at the same time.
Thanks in advance for sharing your thoughts.
Comment